A concrete, fir and glass house stepping down a hillside in the Encino hills, on caissons, drawn and rendered by Akopi Builders as a study.

Concept design. The images on this page are renderings, not photographs of a built home.

A low concrete and fir house behind a street wall, an old live oak at the left
The street front: one low story behind a concrete wall.
Lot
41,600 sq ft, 160 x 260 ft, falling west
Enclosed area, three levels
17,026 sq ft
Counted floor area
13,490 of 13,632 sq ft allowed
Lower level
3,784 sq ft, not counted
Bedrooms
5 suites
Height over the slope
29 ft 11 in at most, limit 30 ft

Akopi Builders drew the house for an imagined hillside lot in the Encino hills, south of Ventura Boulevard, inside the City of Los Angeles hillside rules for size, height, grading and fire. From the street it is one quiet story. Behind it the house steps down the slope in three levels to a long pool and a view over the San Fernando Valley, held on drilled caissons. It has a set of plans, one model behind every image, and every room finished on paper. We made it to show how we think before we build. Look at the images first. Then open the plans.

Plans

A client should notice that the rooms were planned before they were pictured. An architect should notice the counted area held under the hillside cap, the Lower level in section, dug into the hill and open only to the west, every level stepping down inside the 30 ft limit over the slope, and the pool on its own caissons.

  1. P1 Site plan, the whole lot

    The 160 by 260 ft lot, the street on the ridge to the east and the hill falling about 78 ft to the canyon in the west. The house steps down the slope inside 25 ft front and rear yards and 20 ft side yards. The two coast live oaks and the sycamore are kept, and nothing is built under a crown.

    Page P1: Site plan, the whole lot. Concept drawing, not for construction.
  2. P2 Street level

    One story at the street: the entry hall on one line from the front door to the view, the living room, dining room and kitchen across the west glass, the covered outdoor room, the office, two bedroom suites and the four car garage turned to the side court.

    Page P2: Street level. Concept drawing, not for construction.
  3. P3 Garden level

    12 ft below the street and dug into the hill. The primary suite, bedrooms 2 and 3, the family room and the pool side powder room open west onto the pool terrace and the 60 ft infinity edge pool.

    Page P3: Garden level. Concept drawing, not for construction.
  4. P4 Lower level

    24 ft below the street, open to the slope on its west face only, so the city does not count it: the wellness rooms with sauna, steam and cold plunge, a gym, a theater and the wine room.

    Page P4: Lower level. Concept drawing, not for construction.
  5. P5 East elevation, the street front

    From the street the house is one low story, its roofs 14 ft 6 in at the highest. Board-formed concrete, fire retardant treated fir at the roof edges and soffits, and a rift white oak pivot door.

    Page P5: East elevation, the street front. Concept drawing, not for construction.
  6. P6 West elevation, the hillside front

    Three levels stepping down the hill. The pool terrace and the pool stand on grade beams and drilled caissons; the top of the house stays inside the 30 ft limit measured over the slope below it.

    Page P6: West elevation, the hillside front. Concept drawing, not for construction.
  7. P7 Section A, front door to pool

    Cut through the front door, the entry hall, the living room, the family room, the pool terrace and the pool, looking south. The pool sits on its own row of caissons.

    Page P7: Section A, front door to pool. Concept drawing, not for construction.
  8. P8 Section B, through the wellness rooms

    Cut through the south wing, bedroom 3, the Lower level hall and the wellness rooms: all three levels, the retaining walls against the hill, and the caissons under the west end.

    Page P8: Section B, through the wellness rooms. Concept drawing, not for construction.
  9. P9 Section C, the main stair

    Cut through the main stair, all three levels, from the Street level down to the Lower level.

    Page P9: Section C, the main stair. Concept drawing, not for construction.

Nine pages are shown: the site, the three floor plans, the two long elevations and three sections. The rooms, the furniture, the lighting and the outside details are drawn in the model data behind them. Drawings past these are made when a real project needs them.

Selected pages, PDF 9 pages, 1058 KB

Materials

  • Board-formed concrete, pale warm gray

    The base, the walls against the hill, the street wall, the fireplace masses

  • Douglas fir, vertical grain

    Roof edges, soffits, slab edges and the ceilings

  • Dark bronze aluminum

    Every window and door frame, the roof edge metal, the garage doors

  • Clear glass, both panes tempered

    Every window and glass wall

  • Laminated glass guards

    The outdoor room, the terraces, the stair

  • Light gray roof membrane

    Every flat roof

  • Honed black basalt

    The terraces, the pool coping, the kitchen island, the steam room

  • Rift white oak

    The front pivot door, the floors, the joinery, the stair treads

  • Smooth plaster, warm pale gray

    The inside walls that are not concrete

  • Blackened steel

    The kitchen hood, shelves, light fittings

  • Sierra White granite

    The basin in powder room 1

  • Iron glazed stoneware tile

    Powder room 2, by the pool

What it takes to build here

General points, true of a new house on a downslope hillside lot in the Encino hills. None of this is legal advice, and a real project starts with the City and the project's own consultants.

  1. On a hillside the cap follows the slope.

    The City's hillside rules split the lot into bands by steepness, and the steeper the band the less floor area it allows. In the RE15 zone the share runs from 35 percent on ground under 15 percent slope down to 15 percent on the steepest. On this lot that gives 11,360 sq ft, and 13,632 with a 20 percent bonus for wide side yards. This study counts 13,490.

  2. Every solid roof counts.

    A porch or patio under a solid roof counts as floor area; only a lattice roof is left out. So this study's covered outdoor room, 448 sq ft, is in its total.

  3. A level dug into the hill can be free.

    A lower floor is not counted when no more than 60 percent of its outside walls stand more than 3 ft out of the ground. This study's Lower level is open to the view on one face only: 34.6 percent of its walls, so its 3,784 sq ft are not counted.

  4. Thirty feet over the slope, not over the street.

    With flat roofs the limit is 30 ft, measured up from the hillside below each point, so the house has to step down the hill rather than stack. Within 20 ft of the front lot line it may stand no more than 24 ft over the street. This study's highest point is 29 ft 11 in over the slope, at a chimney, and it stands 12 ft over the street.

  5. Grading is capped, the house is not.

    Earth moved for the pool, the terraces and the drive counts against a cap set by the zone and the lot. Digging under the house itself, for footings and a dug in floor, does not. The stricter of the City's two published caps allows 1,600 cubic yards here; this study counts 112.

  6. Trucks keep hours.

    On a hillside lot, hauling for grading runs only from 9 a.m. to 3 p.m., Monday to Friday, and the amount carried off a lot is limited. The schedule on this page allows for it.

  7. The oaks come first.

    Coast live oaks and western sycamores are protected trees in Los Angeles, and none may be removed without a City permit. This study places the house round two old live oaks and keeps the sycamore in the canyon. Nothing is built under a crown.

  8. Most of these hills are in the highest fire zone.

    The City says most of the hillside in this part of the Valley is in a Very High Fire Hazard Severity Zone, and this study is drawn as if its lot is too. So the glass is tempered in both panes, the roof has no vents, the fir at the roof edges and soffits is fire retardant treated, and the terraces are concrete and stone.

How the job would run

Schedule by phase

The phases, in order, for a house like this on a hillside with caissons. Planning numbers for a concept, not a promise.

  1. 1 Preconstruction The drawings are read in full, conflicts are flagged, long lead items such as the glass walls, the sliding doors and the steel are ordered, and the job is priced. Duration: 12 weeks Before construction, beside the permits
  2. 2 Approvals and permits The soils and geology reports, building plan check with the structural design for the caissons and the cantilevers, the grading and hauling permits, fire review, and the City's tree permits. Duration: 44 weeks Before construction, set by the City
  3. 3 Site preparation and access Fencing, tree protection round both oaks and the sycamore, utilities, a working pad at the street and a safe way down the hill, and a survey of the neighbors' houses before digging. Duration: 6 weeks Weeks 1 to 6
  4. 4 Shoring, excavation, caissons and grade beams Shoring where the cut is deep, the dig for the Garden and Lower levels with the soil hauled in the hours the City allows, then the drilled caissons and the grade beams on them, each hole looked at by the soils engineer before steel and concrete go in. Duration: 16 weeks Weeks 5 to 20
  5. 5 Lower and Garden levels The retaining walls against the hill, waterproofed and drained before backfill, the floor slabs, and the board-formed walls, poured lift by lift. Duration: 22 weeks Weeks 19 to 40
  6. 6 Street level and roofs The Street level walls and slab, the steel for the cantilevered floor and the outdoor room roof, and the roof plates over every level. Duration: 16 weeks Weeks 37 to 52
  7. 7 Envelope The roof membranes and drains, the glass walls and sliding doors, the fir roof edges and soffits, and the guards, until the house is dry. Duration: 22 weeks Weeks 49 to 70
  8. 8 Rough systems Plumbing, air, electrical, the elevator, lighting control and audio, all before any wall or ceiling closes. Duration: 20 weeks Weeks 53 to 72
  9. 9 Interior finishes Plaster, white oak floors, fir ceilings, the stair, the kitchen, the two powder rooms, the baths, and the sauna, steam room and plunge. Duration: 34 weeks Weeks 73 to 106
  10. 10 Pool, terraces and landscape The pool shell on its caissons and its vanishing edge, the stone terraces, the drive and courts, planting and brush clearance on the slope, and the outdoor lights. Duration: 32 weeks Weeks 71 to 102
  11. 11 Commissioning and handover Every system is run and set, scenes are programmed, the punch list is closed and the manuals are handed over. Duration: 8 weeks Weeks 105 to 112

Phases overlap, so the weeks are for each phase and not a sum. Construction runs about 112 weeks from mobilization to handover.

Approvals and permits come first and are counted apart, because the City sets that time and the builder does not.

The house stands on drilled caissons and grade beams, and the Garden and Lower levels are dug into the hill behind retaining walls. The soils engineer looks at every caisson hole before it is filled, the oaks stay fenced outside the work, and the walls against the hill are waterproofed and drained before any soil goes back.

Budget structure

The cost categories, in the order they are built, as shares of the whole. Planning shares for a concept, not a price.

  1. Site work, access and utilities Share: 3%
  2. Shoring, excavation, caissons and grade beams Share: 10%
  3. Retaining walls, Lower and Garden level structure, waterproofing Share: 9%
  4. Structure above: board-formed concrete, steel, roof plates Share: 11%
  5. Envelope: glass walls and sliding doors, roofs, fir edges and soffits, guards Share: 15%
  6. Mechanical, electrical, plumbing and the elevator Share: 11%
  7. Lighting, controls, theater and audio visual Share: 4%
  8. Interior finishes: plaster, white oak floors, fir ceilings, the stair Share: 11%
  9. Millwork, kitchen, stone and wet rooms Share: 9%
  10. Pool and wellness rooms Share: 5%
  11. Terraces, outdoor room, drive, landscape and brush clearance Share: 4%
  12. General conditions Share: 8%

This shows how the cost of a house like this is organized, as shares of the whole and with no dollar totals, because a total belongs to a real site and a real set of drawings.

The 100 percent is the hard cost of construction, with the builder's general conditions. The allowance for what the ground can turn up is carried inside the lines where that risk sits. It leaves out the land, design and engineering fees, permits and agency fees, furnishings and financing.

Sample weekly owner report

SAMPLE. This report is an example of the format. None of this work has happened.

Encino Residence, concept study. Owner report, Week 46.

Work completed this week

  • Garden level: the last lift of the board-formed wall at the north end poured; forms off the lift below, ties plugged.
  • Street level: steel outriggers for the outdoor room roof set and bolted, checked against the engineer's drawings before decking.
  • Lower level: waterproofing on the east retaining wall finished and photographed; the drain at its foot run with water.
  • Pool: the shell's west wall formed on its caisson row, the vanishing edge set to level before the pour.

Next two weeks

  • Street level: the slab over the Garden level poured in two halves.
  • Roofs: tapered insulation and the membrane on the low roof over the south wing.
  • Slope: backfill behind the Lower level wall, in lifts, compacted and tested.

Decisions needed from the owner

  • Approve the concrete sample panel: the board pattern, the color and the plugged tie holes.
  • Approve the fir sample for the soffits: grain, oil and the fire retardant treatment.
  • Choose between two basalt samples for the terraces. Both are at the site office.

Selections due

  • The pendant over the dining table.
  • Bath fittings for bedrooms 2 to 5.
  • Loungers for the pool terrace.

Changes

  • Sample change: a second oven is added in the kitchen. The tall oak bank has no free unit, so the coffee station moves to the back kitchen. The kitchen elevation, the plumbing plan and the electrical plan were revised before the cabinet maker's shop drawings. In a real report the cost and the time effect of each change are stated here, and nothing proceeds until the owner signs.

Inspections

  • Passed: steel at the outdoor room roof.
  • Passed: waterproofing, Lower level east wall.
  • Scheduled: pool steel.

Photos

  • Everything about to be covered, before it is covered: the waterproofing on the walls against the hill, the drains at their feet, and the steel in each lift before the pour.
Quality checklist

Checks a careful builder runs. General practice, each one confirmed against the engineer's drawings or the product maker's instructions on a real job.

Caissons and the hill

  • The soils engineer's report is read in full before the caissons are priced.
  • Protected oaks are fenced at the line the arborist sets before any machine arrives.
  • Each caisson hole is looked at by the soils engineer for depth and bottom before steel goes in.
  • Concrete in a deep hole is placed so it does not fall through the steel, as the engineer specifies.
  • Grade beams are poured only after every caisson under them is signed off.
  • Hauling runs in the City's hours, with the truck count logged.
  • Nothing is covered until the inspection is logged and signed.

Board-formed concrete

  • A sample panel is built and approved before production: boards, color, ties and the sealer.
  • Boards are sorted and set level, joints lined up from lift to lift.
  • Pour joints fall in a board joint, drawn on the shop drawings, not left to the field.
  • Every sleeve and tie through a wall against the hill is sealed and photographed.
  • Finished faces are protected until the last trade has left.

Flat roofs in a fire zone

  • The roof is a Class A assembly as the maker lists it, from the deck up.
  • Every roof has a drain at each low point and an overflow beside it.
  • Each membrane seam is welded and probed, and the roof is water tested before the ceilings close.
  • Soffits and edges are fire retardant treated wood or metal, with no vents.
  • Glass is tempered, and the guard glass is the tested system the maker sells.