Encino Residence

Concept study

A house changes on the way. The drawings change first.

No client finishes a house with the list they started with. A room grows, a door moves, a window turns out to look at the wrong thing. That is normal. A builder's job is to keep the house buildable while it happens.

This concept house changed too, more than once, and we used it to show how we handle it.

The first layout put bedroom 4 on the Garden level, behind the rooms that face the view. On a level dug into a hill, a room that far in has no outside wall and no window. So bedroom 4 moved up to the Street level, beside the guest suite, and the Garden level kept its whole west face for the rooms that open to the pool.

Then the pool. Its shell first ran 2 ft into the pool equipment room on the Lower level under it. The pool moved 2 ft west, clear of the room.

Then the ground. When we built the model, it found that the beams under the pool and the beams under the Lower level had been drawn as one, so five of the pool's caissons stood clear of any beam and one wall of the pool had nothing under it. The plan data was fixed, the pool was given its own row of beams, and the section on this page was redrawn from the corrected data.

Some changes made a number worse, and we print the worse one. Height had first been read at the middle of each patch of roof. Read at the downhill edge, where it counts, the outdoor room chimney stands 29 ft 11 in over the slope, not 29 ft 8 in. It is still under 30.

Each time, the order was the same. The drawing changes first. Not a note, not a text message. The plan, the section and the schedule that the change touches are revised, so the next person who opens the set sees the house as it now is.

Then everything downstream follows the drawing, and gets checked. The outdoor dining table was drawn for eight, which left the cook at the grill 21 in to stand. It is now a table for six, and the cook has room. In one rendering a retaining wall on the Lower level came up through the family room floor as a row of steps. The wall was cut back in the model to stop 1 ft under that floor, and the view was rendered again.

Then the owner sees it in writing. A real project gets a written update every week: what was done, what is next, which decisions are waiting, and what each change does to the cost and the schedule before anyone proceeds. There is a sample on this page.

Some things do not change, and we say so early. The cap on floor area, the 30 ft limit over the slope, the rule that keeps a dug in level uncounted, the grading cap and the protected oaks are not open to negotiation on this lot. A wish that crosses one of them gets a clear answer on the first day, not a hopeful maybe.

What this asks of a builder is patience and paperwork. We read the full set before we price it. We keep the drawings current. One person stays accountable from the first meeting to the keys, and you can reach him.

Akopi Builders has been building in Los Angeles since 2014. We ran this house the way we run a real one.

The images on this page are renderings of a concept design, not photographs of a built home.